-finish insulation and drywall
-plaster
-paint
-install water heater
-install gas heater
-install bathroom sink, toilet, and kitchen sink
-get the plumber in again
-get the electrician in again
-get the septic guy in again
-the loft floor
-the downstairs floor
-the staircase
-window and door trim
-sand and paint front door
-sand and finish the upstairs floor
-buy a bed and other furniture we may need
-pick furniture up from Ben's mom
-pick up the co-sleeper from my friend
-several trips to and from Ben's dads to get all of our shit in storage
-buy cloth diapers and diapering stuffs (and then wash them 40 thousand times before use)
-Go to target and spend a freakin' fortune on random crap for the house and the baby
-Move in
Think we can do it all in 4 weeks?